North East Link Project
Location: Melbourne, VIC Australia
Type of work:
- Ventilation Tunnel inclusive of Inverts, ADIT’s & Arch pressure pours,Incorporating 6,400 cubic meters, and 26 arch pours more than 280 lineal meters in distance.
- Manningham to Trinity Tunnel Linning inclusive of Inverts, Cross Passages and Arch pressure pours. Incorporating 20,000 cubic meters, and 61 arch pours more than 920 lineal meters in distance.
- TBM Tunnels Trailing Gantries, Fabrication and Installation of 14 units, which comprised 720 tonnes ACROW proprietary systems.
- Shafts, Retaining Walls, TBM Launch Structure, and other associated Concrete Structures and temporary works Project wide.